Question: 1 / 400

Which protocol is important before initiating a hoisting operation?

Warming up the crane engine

Check before you lift

Before initiating a hoisting operation, the "Check before you lift" protocol is essential because it involves a comprehensive assessment of various crucial factors that ensure safety and efficiency during the lift. This protocol typically includes inspecting the crane itself, verifying load weights, ensuring proper rigging, and confirming that all safety devices are functional.

Conducting this checklist before lifting significantly reduces the risk of accidents and equipment failure. It ensures that the crane is suitable for the intended load and that all conditions are safe for proceeding with the operation, thereby protecting both personnel and equipment on the job site. This proactive approach is a cornerstone of safe crane operation and aligns with best practices in the industry, making it the most critical step prior to any hoisting task.

While warming up the crane engine and ensuring that all team members are present are also important, they do not encompass the comprehensive safety checks required for lifting operations. Checking the weather forecast is valuable but is just one of many factors to consider in the broader context of preparing for a hoisting operation.

Get further explanation with Examzify DeepDiveBeta

Ensuring all team members are present

Checking the weather forecast only